From January of 2018 to April of 2019 I worked as a Project Manager and Site Superintendent for Fortis 17 Construction and Design Lab Development. During this time I oversaw construction and installation of two custom designed modular homes in North East Los Angeles. I was responsible for everything from obtaining permits, coordinating inspections, finding and scheduling subcontractors, negotiating contracts, redlining engineering and architectural drawings, submitting and answering RFI’s, and verifying accuracy and completion of work. As these were modular projects, the majority of the home construction was built offsite in a factory in Oregon while the foundation was built on site. As such, extreme care needed to be taken to verify that all work was accurate. The photos below show the process of one of the homes, 4001 Berenice Place.